Cost Metrics Cost Variance (CV) The difference between a task’s estimated cost and its actual cost: CV = BCWP - ACWP Negative Value = over budget and/or behind schedule Cost Performance Index (CPI) The percentage of work completed per dollar spent CPI = BCWP divided by ACWP ratio > 1 = ahead of schedule and/or under budget << Back Interactive Multimedia ~ School of Applied Engineering and Computing Sciences ~ Sheridan |